According to ChainCatcher citing The Electronic Times, SK Hynix is discussing orders with partners for HBM4 manufacturing equipment, including bonding, cutting and inspection tools. The company aims to have additional equipment delivered and installed in the first half of next year, with some deliveries requested before the first quarter.
The likely expansion site is P&T6 in Cheongju, formerly known as M8. SK Hynix designated the facility as an HBM production site in 2025 and began building HBM production lines there early this year. The company plans to use available space at P&T6 to expand HBM4 capacity, potentially adding more than 20,000 wafers of monthly HBM output at full production.
At its third-quarter earnings call last month, SK Hynix said its DRAM and HBM supply for the three years through 2029 was effectively sold out. A company representative said it is continuing equipment orders according to plan and will respond to market growth.