Texas Data Centers Face Months of Delay, Not a Halt — JPMorgan Favors Grid Equipment

$267260.KS $298040.KS $BTC

J.P. MORGAN | STEPHEN TSUI, VENTO SUEN • 20 November 2026

1. Will Texas policy stop data-center projects?

• Texas holds over 20% of the U.S. data-center pipeline — more than 50 GW (BNEF) — so a slowdown there hits power-equipment demand.

• After the U.S. midterms, J.P. Morgan's expert call was with a senior executive of a Texas-based electric company; permits are already resuming — SpaceX received an air-pollution permit for its Starbase data center.

• With divided state government and Republicans keeping the Senate, sweeping policy change looks constrained; the likelier lever is stricter environmental requirements, delaying some projects by several months — not cancelling them.

• Projects that already meet current rules face lower risk; those still far from approval — including some targeting 2028–29 — are the most exposed to extra requirements or delays.

2. How do developers get power quickly?

• Time-to-power is critical, so developers procure whatever generation they can get quickly — including older, less-efficient thermal units as bridge power, then switch to cleaner generation and keep the old units as backup.

• Regulators could cap those bridge units' operating hours or capacity factors — the transitional option is not guaranteed.

• Gas-fired combined-cycle units are relatively acceptable in Texas, while renewables alone cannot reliably meet data-center loads; dispatchable generation stays necessary.

• Hybrid grid and behind-the-meter supply plus load flexibility speed connections; smaller distributed sites connect faster than gigawatt-scale campuses — but large transformers remain a bottleneck, with lead times of 3.5+ years.

3. What about transmission and grid spending?

• 765-kV transmission is the long-term fix, but siting, landowner opposition and political pressure stretch timelines — even the first approved project, from the Permian Basin to Texas load centers, was temporarily paused.

• In the expert's base case, grid capex stays intact, growing 8% a year, with only slight downside if data-center delays become meaningful.

4. Which equipment names does J.P. Morgan favor — and what are the risks?

• J.P. Morgan prefers companies with greater utility and grid exposure, which face lower order delay/cancellation risk — and sees good value in HD Hyundai Electric and Hyosung Heavy at low-to-mid-teens one-year forward P/E.

• HD Hyundai Electric (267260.KS): Overweight, price target ₩925,000 (28 Oct 2026, cut from ₩1,130,000 on 14 Oct); price ₩415,500 at the 19 Nov close.

• Hyosung Heavy Industries (298040.KS): Overweight, price target ₩3,150,000 (30 Oct 2026, cut from ₩3,800,000 on 14 Oct); price ₩1,796,000 at the 19 Nov close.

• Watch the constraint: U.S. import restrictions bite hardest on grid-facing equipment; behind-the-meter gear has more flexibility if adequately isolated from the grid.

#DataCenters #Texas #PowerGrid #AIInfrastructure #Energy

Source: J.P. Morgan, 20 November 2026. Based solely on the report provided; expert views and forecasts are not guaranteed. For reference only; not investment advice.