PJM plans to cut interconnection studies for large load projects from two years to one—not by doing fewer reviews, but by studying generation and load together and moving financial requirements earlier in the process. For now, PJM is the only source for these figures.

The key to speeding things up is to first weed out the paper projects clogging the queue. This assessment will no longer hold if FERC does not approve the plan, or if large numbers of projects entering the new process still withdraw.