OpenAI's 3.2GW Georgia Project Faces a New Risk: Legal Permission to Build.
Three Georgia residents have filed a civil RICO lawsuit against OpenAI affiliates and local officials over Project Camellia, a proposed $20–30B AI data center campus.
The plaintiffs allege that NDAs, closed-door negotiations and improper zoning procedures kept residents out of key decisions.
These are allegations, not judicial findings.
But the investment implications extend beyond this lawsuit.
AI infrastructure projects need more than GPUs, financing and grid connections. They also need legally durable land-use approvals.
A project can secure customers and power commitments yet still face delays if its permitting process is challenged.
For a proposed 3.2GW campus, even a modest delay could affect construction schedules, equipment deployment and revenue recognition.
The next AI infrastructure bottleneck may not be electricity alone. It may be the legal ability to turn contracted power into an operating data center.