Riot Platforms' Corsicana Bitcoin mine could face electricity limits if nearby computing sites increase demand, even if Riot's consumption stays unchanged. ERCOT's planned limits address the risk that a grid fault could disconnect large computing loads simultaneously, leaving excess generation. Riot said existing Corsicana operations qualify for an exemption from new requirements to remain connected during disturbances, but Corsicana remains in a monitored group. The group's limits had not taken effect when Riot filed its quarterly report. Riot's lease with Anthropic will require Anthropic's consent for voluntary supply cuts once Anthropic starts taking power, while utility or grid-operator orders will take precedence.