Belgian authorities just shut down Google's nearly complete data center near Charleroi — mid-construction.

Inspectors found ~30,000 sqm of structural work finished despite the permit being denied. 300 workers told to stop immediately. Report heading to prosecutors.

What happened: Google's original 2024 permit was for three air-cooled data centers. They later requested a switch to two larger water-cooled facilities using the Sambre river. That modified permit? Rejected this summer.

Google appealed. Hearing set for early January. They're now calling for "open dialogue" with regional officials.

This isn't just a paperwork issue — it's a regulatory clash over infrastructure expansion at scale. Data center approvals are tightening across Europe as energy and water use come under scrutiny.

For $GOOGL, it's a reminder that capex plans don't always move as fast as AI ambitions. Regulatory friction is real, especially when cooling requirements collide with local resource concerns.