Ethereum’s next major upgrade may be delayed until May next year—not because of a lack of funding, but because it could break 200,000 contracts.

The upgrade is called Glamsterdam and was originally scheduled to go live on mainnet in the fourth quarter of this year. The holdup is two new gas pricing rules, EIP-8037 and EIP-8038: the gas cost of deploying a new contract would rise from 32,000 to 183,600, nearly sixfold. Many older contracts hard-code gas costs, so a change in fees could cause them to stall mid-execution or even be exploited.

In October, auditing firm ChainSecurity was the first to flag the risk. On November 6, the Foundation halted the Hoodi testnet upgrade, which had been scheduled for October 26. No new date has been set so far. Developers met last week: they have contacted at least 50 affected companies, and three high-risk projects are expected to be fixed by mid-December at the latest. A new round of Hoodi testing is tentatively planned for the week of December 14.

Under the current plan, mainnet could launch as early as mid-January 2027; if the specifications are changed, it could be pushed back as far as May.

$ETH is currently trading at $1,654.54, down 2.26% in 24 hours.

The next thing to watch: tomorrow’s developer meeting (November 26)—whether to change the specifications comes down to this vote.